Sheet piles and foundation piles can be installed using different methods. A monitoring plan therefore needs more information than “piling will take place”. Ask for the method, locations and planned sequence. This provides a better basis for deciding which neighbouring buildings and measurement points matter.

Follow the work as it moves

Work may start at one end of the site and move closer to a house later. Keep the programme with the monitoring plan and agree who reports changes in location or method. The monitor needs a suitable, documented position, not simply the easiest place to reach.

Include information about buildings with existing damage or other relevant features. A pre-work inspection and activity log can provide the context needed to understand the readings. NGI’s research into excavations and damage reduction explains why follow-up of neighbouring buildings belongs alongside groundworks planning.

Ask for traceable recordings

When investigating an event, its date, time and working location are important. If several activities take place together, the log should distinguish them. “Sheet piling all day” provides little help when explaining one recording.

Also establish what happens after an alert and who can change the working method. An automatic message is useful only if its recipient knows what to do next.

The report should allow the measurement point and work period to be identified again. Describe the piling or sheet-piling project if you need help organising measurements and reporting around affected buildings.

What to check

  • Obtain the method and sequence for the piling work.
  • Link recorded events to the correct working location.
  • Establish who responds to alerts during the work.