A monitor records an event at 13:42, but the work log says only “excavation after lunch”. Much of the context is then lost. Measurements are easier to use when activities and observations have both a time and a location.
Use a consistent time reference
Establish which time the report displays, especially when data moves between systems or a project spans a daylight-saving change. Retain the time information in original files. A manually altered clock or a screenshot without a date can create avoidable uncertainty.
Instruments may provide time-synchronisation functions, but the report and work log must still align. Check this early rather than discovering a difference while investigating a disputed event.
Record what another person can use
A useful entry may include the working location, activity, start, finish and relevant changes. “Breaking concrete at the north corner from 13:30 to 13:50” is more informative than “machine operating”. Keep the detail proportionate to the task so the log remains practical during the work.
A resident’s observations can be attached with their source identified. Distinguish when something was discovered from when it is thought to have happened. If the time is uncertain, say so.
During a review, an event should be traceable from the graph to the log and then to someone who can explain the activity. Contact us about reporting and event follow-up if the measurements and work information in your project are not connected clearly enough.
What to check
- Check the time reference used in reports and work logs.
- Include location and activity with start and finish times.
- Distinguish discovery time from the assumed event time.