The machinery has left, but the monitoring job is not complete until the records are assembled. A clear final report makes it possible to revisit the measurements if questions arise later.

Check that the period covers the work

Establish whether compaction, breaking or other activities covered by the monitoring plan remain. The end date should follow the relevant work. If equipment is removed earlier, the records should identify the period without coverage.

Before removal, record the measuring point, equipment identifier and final status. Take photographs showing where the instrument was installed. Any relocation during the project should remain traceable.

Request a usable record

The final report should summarise the monitoring period, measuring points, events and gaps. References to alerts should let the reader find the original record and the response that followed.

Agree how the underlying data will be delivered or retained. A screenshot of a graph is difficult to investigate later if the period, units or settings are missing. File names and folders should make it easy to connect the report to the right site.

Check whether the report covers every location in the plan. An unexplained missing point should be resolved before the monitoring is signed off.

Compare the building with its earlier condition

If a closing building survey is included, it should refer to the earlier photographs and records. Describe new observations by location and extent. Measurement data and building inspections address different aspects of the case and should be readable together.

Ask us to review the closing records if measurements, alerts or photographs from the construction period are difficult to piece together.

What to check

  • Check whether vibration-generating work remains.
  • Account for every measuring point and data gap.
  • Agree delivery or retention of underlying records.