When a design changes during a project, compare it with what the municipality actually approved. Do this even if the adjustment seems small or convenient on site. DiBK explains that permission concerns the approved proposal. Clarify the revised arrangement before carrying it out.

Locate the approved version

Find the decision and the drawings it refers to. Check that they represent the latest permission and read any conditions. An old quotation or a contractor’s working drawing may show something different from the proposal the municipality considered.

Prepare a short change record with the reason and relevant dimensions. Show where a window would move, how a room would change or which part of an extension would be different. Use drawings that allow the approved and proposed arrangements to be compared without searching through many files.

Identify the consequences

Consider position, height, use and technical details together. A new window can affect both the facade and the structure around the opening. Moving a wall may affect rooms or services that were not part of the original discussion.

Where the project has a responsible applicant, have that person handle the amendment question. The municipality can also explain how the matter should be submitted. Notification needs to be considered where neighbours are affected. Give everyone assessing the question the same current description.

Keep the site and records aligned

Before work on the change begins, make sure everyone uses the right drawing revision. Mark earlier sheets as superseded in the working folder and give current files clear names. Confirm which version the contractor is pricing and building from.

Retain clarifications and decisions, and add the change to the record used when closing the case. This is easier than reconstructing the sequence after the work is finished. Ask Budsjekk for help following up a project change.

What to check

  • Find the decision and approved drawing revision.
  • Mark the proposed changes and affected documents.
  • Clarify amendment and notification requirements before carrying out the change.